“We
found that the program, now in its seventh year, is meeting its
estimated acquisition cost. However, the program office projects that
Boeing will not deliver the first 18 fully capable aircraft until May
2019—21 months later than initially planned,” the Government
Accountability Office (GAO) said in a recent report. Boeing won the
competition to develop the KC-46 aircraft in February 2011.
The
total acquisition cost estimate for the KC-46 refueling tanker
aircraft remained stable over the last year at $44.4 billion. This is
about $7.3 billion, or about 14 percent, less than the original
estimate of $51.7 billion, the GAO said.
Boeing
faces the following risks and challenges and is trying to address
them:
•
updating
test aircraft to the correct configuration to complete remaining
tests;
•
completing
flight tests at a pace that is almost double its monthly average;
•
updating
test plans to reflect a more realistic schedule for certifying
aircraft, such as F-16 fighters and C-17 cargo planes, to be refueled
by a KC-46;
•
retrofitting
production aircraft to their final configuration for delivery; and
• fixing
a critical deficiency to keep the boom from contacting receiver
aircraft outside the refueling receptacle.
The
program plans to eventually field 179 KC-46 aircraft in total. These
aircraft are intended to replace roughly one-third of the Air Force’s
aging aerial refueling tanker fleet, comprised mostly of KC135
Stratotankers.
No comments:
Post a Comment